ITC Atık Prosesi · Ankara, Turkey

A 2x18 MW biomass energy plant installed at ITC Enerji's facility in Ankara, Turkey.

Location
Ankara, Turkey
Year
2020
Capacity
2x18 MW
Fuel
Refuse Derived Fuel (RDF)

About the client

ITC Enerji is an industrial wood processing company based in Ankara, Turkey. The company operates continuous manufacturing processes with high demand for reliable thermal energy solutions.

EPC and engineering scope

Bersey undertook the EPC and engineering scope for turnkey delivery of the energy facility. Engineering services, system design and integration were addressed in line with the client's process requirements and operating conditions. The scope brought together the use of production residues as an energy source, the design of systems to meet applicable environmental requirements, and the work required for turnkey delivery.

Plant design

The plant is designed for wood waste combustion from production processes. 2x15 MW Thermal Oil for ORC, 8 MW Thermal Oil.

Scope of supply

  • Moving Floor Fuel Silo
  • Fuel Conveyor and Bunker
  • Oversize Fuel Separator
  • Bersey Combustion Stepgrate
  • Refractory in-lined Combustion Chamber
  • Combustion Air & Gas Recirculation System
  • Ash Cooling & Extraction System
  • Radiation & Convection Heaters
  • Automatic Retractable Soot Blowers
  • Steel Structures, Platforms and Stairs
  • Electrical System & PLC Control Unit
  • Refractory Application
  • Piping & Ducting
  • Flue Gas System & Emission Control System
  • Pumps Stations & Collectors
  • Emergency Coolers

Energy system capacities

  • 2x15 MW Thermal Oil for ORC
  • 8 MW Thermal Oil